2011 Engineering Project Update
Spring 2011
PROJECT NO. STP-E-CO64(108)--8V-64 BIKE TRAIL
Location: Highland Acres Rd. and Iowa Ave.
Contractor: Con-Struct Inc.
Construction Activity: Construction of new bike trail along Highland Acres Road and Iowa Ave. that will connect the existing Marshalltown trail with the existing HWY 330 to Baxter bike trail.
Duration: Project is nearly completed with only fencing remaining to finish.
PROJECT NO. BRS-C064(106)--60-64 LISCOMB BRIDGE
Location: Iowa river bridge on Marble Road approximately 3/4 mile West of Knapp Ave. or 1.5 miles West of Liscomb.
Contractor: Godberson Smith of Ida Grove, Iowa
Construction Activity: Contractor is finished with the exception of seeding.
Duration: The road is open.
GRANULAR RESURFACING
DIVISION 1
Location: Covers the Northeast ¼ of the county from Knapp Ave. East and from East Main Street Road North.
Contractor: Cessford Construction Inc. from Le Grand, IA.
Construction Activity: Gravel roads receive new rock.
Duration: Project is completed.
DIVISION 2 & 4
Location: Covers the Southern ½ of the county from Highway 30 South.
Contractor: Martin Marietta, rock will come from their Ferguson quarry.
Construction Activity: Gravel roads receive new rock.
Duration: Project completed.
DIVISION 3
Location: Covers the Northwest ¼ of the county from Knapp Ave. West and from Highway 30 North.
Contractor: Knife River Corporation, rock will come from their quarry located north of St. Anthony on S57
Construction Activity: Gravel roads receive new rock.
Duration: Project completed.