Marshall County Courthouse Renovation Meeting
| What | Meeting |
|---|---|
| When |
2010-01-19 from 10:00 to 11:00 |
| Where | Courthouse, Supervisors' Conference Room |
| Add event to calendar |
|
- WELCOMING REMARKS (Todd Kelley)
- Introduction of attendees
- Courthouse door and window replacement project - scope and objectives
- Project status
- Door replacement
- Window replacement
- PRESENTATION BY O.P.N. ARCHITECTURAL FIRM (Brian Lane)
- Window replacement project
- PRESENTATION BY STATE PRESERVATION OFFICE (Paula Mohr and Jack Porter)
- Preservation objectives and standards
- Funding by grant programs
- GROUP GOAL SETTING AND TIME LINE DEVELOPMENT FOR DOOR PROJECT
- Design options for door replacement – process
- Who and when
- Preliminary approval target – team and supervisors
- Obtain quote/s
- Submit package to county supervisor's for approval
- Prepare and submit grant application (due mid May 2010)
- Grant awarded (payable in July of 2010)
- Let contract/s and establish implementation schedule
- Design options for door replacement – process
- GROUP GOAL SETTING AND TIME LINE DEVELOPMENT FOR WINDOW PROJECT
- From Item II (?)
- OPEN DISCUSSION
- CLOSE MEETING